Pontal – Station building
The completion of the separation wall between the station and the garage completed the concrete works the valley station.
In the coming days the first ropeway facilities will be on site.
Material Ropeway T2
The material ropeway that was used for the line assembly of the first section was disassembled and now awaits the next spring to reappear on the second section.
Torino Refuge
We are completing the renovation of the tunnel and staircase connecting the buildings. The new facility will be available for the forthcoming reopening of the lifts after the break maintenance.
Pavillon – last concrete castings
With the casting of the slab of station, the concrete structures of first section are terminated. The construction site begins to prepare for winter closure.
Platforms in Pontal
Platforms of Pontal intermediate station are completed.
Pavillon Station
At Pavillon have already been completed structures of the first two floors of the valley part of the building. On the floor under construction will disembark tourists arriving from Pontal.
First snowfalls
The first snowfall whitened the peaks over 3000 does not stop the construction of Punta Helbronner where activities will continue at least until mid-October.
Tower 2
As expected the last tower of the first section is almost completely assembled. With a height of 52 meters will be the highest of the entire project.
Punta Helbronner – Excavation completed
With the completion of the room at the bottom of the gallery that will house the water tank for fire suppression systems, the underground excavation activities are completed.
The well – a cylinder of concrete
Without stopping the crews take turns at the end of the tunnel for complete setups that will allow in ten days to start the building of concrete cylinder. Another important and complex operational phase kicks off.