Funivia 2° Tronco – Completato il Sostegno 2

Strutture, scarpe, guide vettura, rulli e in testa due grandi segnalatori color arancio.
Il sostegno n°2 a fianco del rifugio Torino è completato.

Trasferimento funi Portanti al Pavillon

Sono iniziate le operazioni di trasferimento delle 4 funi portanti che in autunno saranno posate sul 2° tronco.
Ogni fune viene singolarmente issata da Pontal fino al Pavillon dove viene riavvolta.

Carpenterie Pavillon

After the completion of the fitting of the roof of the boarding platform of the 2nd section, continues the installation of large beams to cover the multimedia room.

2nd Section – 2nd tower

After the cleaning near the terrace of the Old Torino hut, assembly of tower 2 has begun.

Pt. Helbronner

Thanks to good weather assembly of steel structures restarts also in Punta Helbronner. The station is taking shape.

2nd section – Machines room

In less than 10 days even electro-mechanical equipment of the 2nd section have been implemented. The drive pulley of 10 ton is in its place.

Pontal parking

Despite the snow continue works on foundations of underground parking.

Carpenterie Pavillon

Dopo il completamento del montaggio della copertura del piano imbarco del 2° tronco, prosegue la posa delle grandi travi di copertura della sala multimediale.

Funivia 2° Tronco – Sostegno 2

Dopo aver sgomberato la neve a fianco della terrazza del rifugio Torino Vecchio sono iniziati i montaggi delle carpenterie del sostegno funiviario.

Punta Helbronner

Complice il bel tempo riprendono le attività di montaggio delle carpenterie metalliche anche a Punta Helbronner. La stazione sta prendendo forma.