Cabins of 1 section
Cabins of 1st section are now on the construction yard.
First Snowfall in Punta Helbronner
First snowfall covered the structures of Punta Helbronner. Mountings will continue until weather conditions will permit.
Untitled-en
The boarding platforms of the second sectioon Pavillon – Punta Helbronner begins to take shape. From a few days a new webcam allows you to follow the assembly in Pavillon Station
Untitled-en
After the wooden plank which outlined the precise shape of the cover, start the installation of Aluminiumtitanium that will give the station its final appearance.
PUNTA HELBRONNER – Metal structures
The first metal structures of the “Trident” outline the future arrival of the cable car.
Section 1 – Track ropes are mounted
During 30 days of works, track ropes are mounted on the line. We are mounting traction rope supports using the rescue carriage, then we will mount traction rope.
PONTAL – Roof coverage
With the laying of the corrugated steel supporting roof structure is complete.
Starting next week will begin the installation of the final coatings.
Line 1 – Tensioning of track rope
Slowly the coil of track rope is emptied and the head of the rope reaches the Pavillon.
PAVILLON – Metallic structures
With the installation of the first metallic elements the top station of first section is taking shape.
Line 1 – Ropes tensioning
A helicopter threw a 10 mm rope from Pavillon to Pontal. From this moment begins the installation of the cables.