PUNTA HELBRONNER – Structural well
Concrete structures are completed, stairs and elevator rails are mounted.
PAVILLON – Rope saddles
Today was mounted the rope saddles of 1 section top station, at Pavillon intermediate station.
PONTAL – The station is taking shape
With the installation of central beams and the west side you can begin to perceive the shape of the final structure of the Pontal station.
PONTAL – Main beams
Have been completed the two main reticular beams of the roof. Mountings will continue with the secondary arc beams.
PONTAL – Coverage status
After completing the first foundations composed of 4 columns each, was today hoisted the first element of the main beam.
Pontal – Station coverage
Began today mountings of steel structures of the station’s coverage in Pontal.
Pontal – Engine room
In February the Doppelmayr completed the assembly of the machinery in the engine room of Pontal, 1st section.
Winter closure
Again this year, construction will stop for the winter. Punta Helbronner, Rifugio Torino and Pavillon are closed.
Only in Pontal are continuing some construction activities within the building.
PONTAL – Station saddles
The mounting of the saddles of station concludes the first phase of installation of the electromechanical station.
In spring 2013 will begin assembly in the winches room.
Pontal – mechanical assembly
Yesterday began works for installing the portal that will support the “rope saddles”.