Carpenterie Pavillon
After the completion of the fitting of the roof of the boarding platform of the 2nd section, continues the installation of large beams to cover the multimedia room.
2nd Section – 2nd tower
After the cleaning near the terrace of the Old Torino hut, assembly of tower 2 has begun.
Pt. Helbronner
Thanks to good weather assembly of steel structures restarts also in Punta Helbronner. The station is taking shape.
2nd section – Machines room
In less than 10 days even electro-mechanical equipment of the 2nd section have been implemented. The drive pulley of 10 ton is in its place.
Pontal parking
Despite the snow continue works on foundations of underground parking.
Pontal construction site
Snow removal of construction site of Pontal was completed. Next Monday on Pontal works will resume.
1st Ropeway section completed
At the end of the setup by Doppelmayr technicians , the internal testing of the system was successful completed.
The electro-mechanical works of the first section were completed with more than 6 months ahead of the schedule.
Winter closing
From the end of November to mid-December were gradually finished exterior work in the areas of Pavillon and Punta Helbronner, while some internal activities will continue inside during the winter.
Pontal Station
Control Room was completed, setup of the electronic devices ongoing
Cabins on the ropes
Today at 17.15 the two new cabins crossed on the line for the first time.