Carpenterie Pavillon
After the completion of the fitting of the roof of the boarding platform of the 2nd section, continues the installation of large beams to cover the multimedia room.
2nd Section – 2nd tower
After the cleaning near the terrace of the Old Torino hut, assembly of tower 2 has begun.
Pt. Helbronner
Thanks to good weather assembly of steel structures restarts also in Punta Helbronner. The station is taking shape.
2nd section – Machines room
In less than 10 days even electro-mechanical equipment of the 2nd section have been implemented. The drive pulley of 10 ton is in its place.
Pontal parking
Despite the snow continue works on foundations of underground parking.