Carpenterie Pavillon

After the completion of the fitting of the roof of the boarding platform of the 2nd section, continues the installation of large beams to cover the multimedia room.

2nd Section – 2nd tower

After the cleaning near the terrace of the Old Torino hut, assembly of tower 2 has begun.

Pt. Helbronner

Thanks to good weather assembly of steel structures restarts also in Punta Helbronner. The station is taking shape.

2nd section – Machines room

In less than 10 days even electro-mechanical equipment of the 2nd section have been implemented. The drive pulley of 10 ton is in its place.

Pontal parking

Despite the snow continue works on foundations of underground parking.

2nd crane assembled

Assembly of the second Pointe Helbronner crane was completed with the help of a high performance Kamov helicopter; the two cranes will allow transporting materials from the Rifugio Torino work site to the Pointe Helbronner site.

Tunnel

The excavation work for the tunnel connecting Pointe Helbronner – Rifugio Torino was started, with the laying of the first centerings and advancing the first metres; view our PhotoGallery!

Work status

The work site cableways and cranes near Rifugio Torino are being assembled.